Question: How would you set up and lay out a test plan for your system? (Spread sheet or website)

Add new “post” to add your comments, or “leave comment” below. Make sure to tick the Info 1 Topic 9 : Testing CATEGORY.

12 thoughts on “

  1. How should a test plan be structured?
    1.Number each test plan
    2.Explain briefly what you are testing for
    3.Explain briefly how a test is constructed
    4.Give the test data that is to be used
    5.Have a column for expected results
    6.Have a column for actual results
    There you go…

  2. I would recommend making a table of the types of data and state whether the data you have entered is valid or invalid. Include what it gives you as a message to show proof.

  3. Remember that data is not just about numbers, but can also be images videos and sounds. So erroneous data for sound could be that the sound file is corrupted.

  4. Normal Data- test data entered that should be accepted by the ICT solution for processing.

    Erroneous Data- data that is ridiculous or totally unsuitable

    Boundary Data (EXTREME data)- test data entered which is at either side of the limits imposed by a range check and the numbers of the range checks themselves.